Construction & Installation

Installation is where everything comes together. Within hours or days, modules manufactured and fitted out in our factory are installed on site, bringing the building to life.

Your site and building take shape together

One of the biggest advantages of offsite construction is that site works and manufacturing can happen at the same time.

While foundations and other site works are underway, the building is being manufactured and fitted out in our factory. By the time the site is ready, the modules can be ready to ready for delivery and installation.

This parallel approach can shorten the overall construction programme by up to 50%, reducing time spent building on site, exposure to weather and disruption, and bringing projects closer to completion sooner.

Up to 50% faster

From busy urban sites to regional towns, alpine environments and remote locations, every site brings different challenges.

By completing more of the building in the factory, we reduce what needs to happen at its final location. That can mean less reliance on local trades in regional areas, less disruption on site, or less time building in exposed conditions.


Less disruption on site

Installation and finishing works often takes place alongside existing buildings and the people using them. By completing more of the building offsite, we reduce the time, noise, traffic and number of trades required on site.

Carefully planned installation windows help schools, hospitals and other operational environments continue functioning with minimal disruption.

Delivering in complex environments

From a new MRI facility at the Royal Women’s Hospital to the rebuilding of Lismore South Public School, these projects demonstrate how modular construction can be delivered in complex environments, minimising onsite disruption and accelerating installation.

Royal Women’s Hospital MRI Relocation

Delivered in response to Melbourne’s Metro Tunnel Project, the Royal Women’s Hospital MRI facility was manufactured offsite and installed on the hospital’s upper levels to protect critical equipment from electromagnetic interference. The accelerated construction program minimised onsite disruption, allowing hospital operations and essential diagnostic services to continue uninterrupted.

 

Lismore South Public School

Following the devastating 2022 Northern Rivers floods, Lismore South Public School was rebuilt to provide a new, resilient learning environment for the local community. Delivered for School Infrastructure NSW in partnership with ADCO Constructions and Pedavoli Architects, the project used modular construction to accelerate delivery, the project reflects a shared commitment to rebuilding critical education infrastructure across the region.

 


Partner with us

We work with head contractors to bring the benefits of industrialised construction to projects of all scales.

Through our integrated design and manufacturing platform, we provide the expertise, systems and hands-on training to help construction partners deliver modular projects safely, efficiently and at scale.

-